Should You Introduce the Equipment? JIAHON Completes the Evaluation Report for You

Process equipment introduction · Engineering evaluation service

pFMEA risk analysis + simulation testing + ROI estimate — a complete basis for decision (case: evaluating the introduction of an SPI machine)

Whenever an equipment decision comes up, factories often face one of two situations: engineers want to buy but can’t clearly explain the return on investment, or management wants numbers but nobody can pull together a complete evaluation report. That gap often leaves a worthwhile investment stuck in internal discussion for a long time. What JIAHON’s engineering team offers is not just an equipment quotation, but a complete evaluation service from process risk and technical verification to financial estimates — so engineers and management speak the same language and make a well-founded decision together.

Step 1 Define the problem: where the current state falls short

In this SPI evaluation case, the customer’s current process had print specifications set, relied on first article inspection (FAI) for quality confirmation, and used only sampling inspection during production. On the surface it was controlled, but three core problems were not solved:

  • ⊗ Paste volume: solder paste is not solid and deforms easily during handling and measurement; sampling is not accurate enough to measure it precisely.
  • ⊗ Print offset: X-Y offset is easily missed under sampling; by the time AOI after reflow or a test station catches it, a batch of defects has already gone through.
  • ⊗ Foreign-material contamination: fibers, dust and other contamination are hard to cover fully by visual or sampling checks, with no real-time, complete monitoring.

Core problem: quality assurance relied too heavily on FAI, without real-time, complete process monitoring. It was not that specifications were set wrongly, but a structural gap in the existing inspection method.

Step 2 pFMEA risk quantification: which problem to solve first

Saying “there is a problem” is not enough; management needs to see the priority of risks. JIAHON’s engineering team used pFMEA (process failure mode and effects analysis) to calculate the RPN (risk priority number = severity × occurrence × detection) for the three risk items:

Risk itemSeverity (S)Occurrence (O)Detection (D)RPN
Abnormal paste volume — high risk878448
Print offset (X-Y) — medium risk658240
Foreign-material contamination (fibers, dust)576210

The conclusion is clear: abnormal paste volume has an RPN as high as 448, a high-risk item, and the existing sampling method detects it poorly (D = 8 means weak detection). This number turns “should we introduce SPI” from a gut call into a well-founded decision.

Step 3 Technical verification: can the equipment meet the target

With the problem defined, the next step is to confirm the equipment can solve it. JIAHON helped the customer run actual simulation tests on the SPI machine to verify two key indicators — inspecting 34,243 pads in total, extrapolated to full production at a 1:10 ratio:

  • ⏱ Cycle time test — 150 seconds: 15 seconds per run including loading and unloading, extrapolated to 150 seconds for a full strip, then compared with your line’s cycle time to confirm it keeps up. This number directly answers “can this machine keep up with our output?”
  • 🔁 Repeatability test — very low STDEV: 30 consecutive inspections of a single sample gave a very low standard deviation, showing the machine does not drift with operator or environment and that results are highly consistent.

Besides cycle time, three other figures are common in technical verification on the line:

  • Paste thickness baseline. One printer acceptance report printed 15 boards in a row and measured paste thickness on 0201 pads against a 0.06–0.10 mm specification, grading coverage as A (>90%), B (80–90%) and C (<80%). Measure a round the same way before introducing SPI, so there is a baseline to compare against afterward.
  • Measurement repeatability. Measure the same board several times and look at the variation in SPI readings; this is the measurement system’s GR&R, which the NIST/SEMATECH e-Handbook of Statistical Methods lists as a method for evaluating gauge error in production (Section 2.4).
  • Acceptance basis. Acceptance of paste printing results can be compared with IPC-7527 (requirements for solder paste printing; table of contents); SPI judgment thresholds should align with it to avoid over-rejecting on one side and missing defects on the other.

Step 4 ROI estimate: is the investment worth it

Once it is technically feasible, the financial question is the last gate. JIAHON made estimates from the customer’s actual production data, calculated as follows (annual production value = annual output × value per unit; annual saving = annual production value × yield improvement; payback years = total equipment investment ÷ annual saving):

ItemScenario 1 (conservative): yield +0.5%Scenario 2 (reasonable): yield +1%
Annual savingAnnual production value × 0.5%Annual production value × 1%
Payback yearsTotal equipment investment ÷ annual savingTotal equipment investment ÷ annual saving (about half of Scenario 1)

Double the yield improvement and the annual saving doubles, roughly halving the payback period. Combined with the pFMEA risk analysis, this method turns “introducing SPI” from an engineering department’s technical recommendation into a financial decision management can accept.

How to write SPI into the control plan on an SMT line

Once SPI is bought, it is only truly used when it is written into the control plan. Practices in the engineering records:

  • Frequency: every board, every pad. Several SMT control plans write paste printing as “SPI 100% inspection, every board, every pad,” with manual paste thickness measurement (5 points at each changeover) kept for first article and comparison.
  • First article can be handed to SPI. An evaluation of a new SMT line says production starts only after a first trial print has its paste thickness confirmed, and with inline SPI this step can be done by the SPI; but then all print-station problems depend on SPI, so choose a stable machine.
  • Use SPC to decide on early stencil replacement. The same evaluation reminds you to watch the SPI’s SPC closely; when a trend becomes abnormal, replace the stencil early.

For pFMEA scoring, see AIAG’s FMEA reference manual (FMEA-4); this site’s “How to fill in a PFMEA: S, O, D scoring and RPN” also has a paste printing station example.

Frequently asked questions

Q1: Do I need both SPI and AOI? They do different jobs: SPI measures paste volume, area, height and offset after printing; AOI checks parts and joints after placement or reflow. When the share of defects from the print station is high, SPI can stop them before parts are placed, where rework cost is lowest.

Q2: How long does it take for SPI to pay back? Use this article’s formula: payback years = total equipment investment ÷ (annual production value × yield improvement). Estimate the yield improvement from your actual FPY before introduction and the share of print-related defects; don’t simply apply another plant’s figures.

Q3: 3D or 2D SPI? Measuring paste volume needs height information, so SPI is generally 3D; 2D can only see area and offset. A printer’s built-in 2D inspection can give coverage alarms but cannot replace volume measurement.

What JIAHON provides is not just equipment, but a decision service

This evaluation case shows the full capability of JIAHON’s engineering team in equipment introduction services:

  • Step 1 Process problem definition
  • Step 2 pFMEA risk quantification
  • Step 3 Equipment simulation testing and verification
  • Step 4 Financial ROI estimate report

You don’t need to find consultants, research data or build spreadsheets yourself — from defining the process problem, quantifying risk and simulation testing the equipment to the financial ROI estimate, JIAHON turns “should we buy it” into a report management can use directly to decide. If your factory is evaluating the introduction of any process equipment, or needs an investment evaluation report to convince management, please contact JIAHON’s engineering team.

Also worth reading

Before 100% SPI, reduce defects at the source. SPI catches errors after printing; good stencil cleaning stops errors from happening in the first place. Together they make a complete print quality control strategy — the stencil cleaner keeps the stencil clean before every print, and SPI inspects every print in real time; you need both. → JIAHON electric stencil cleaning machine JHPBT-1000X